Camfaud special project team completed a complex pipeline pour Saturday night/Sunday day at Liverpool Street Station. The project involved installing a riser and 200m pipeline to pump 75m3 on platform 2/3 in partial station closure. Using our Eco Pan with blow out lid we were able to safely clear the line with compressed air.
Camfaud provided:
- AutoCAD work for design of riser
- RAMS for pipeline and pump set up
- 2 x Shifts with PTS/TVP support Eco Pans leaving no waste concrete on site from the hopper, pipeline and pipe wash facility.
Bring on the next phase in a few weeks’ time!
Big thanks to the team who attended site and planned the works.