Midland Metro Alliance – Broad Street track bed

We have recently completed the longest continuous concrete pour on the Midlands Metro, to date. On the hottest day of the year, we placed approximately 360 cubic metres of fibre reinforced concrete into a 300 linear metres run of track bed along Broad Street.

Camfaud supplied two working, high pressure, concrete pumps, one standby pump and three pump operators. We also supplied a crew of linesmen to strip back, clean and stack the high pressure delivery pipes. The pumps were set up at each end of the job, working from the centre out.

This pumping plan was devised to ensure that the pour was completed in a timely fashion and, with hot weather forecast, there was no danger of having the concrete go off in the pumps or pipeline, and no problem with cold joints.

Hinckley Point C – New UK record for a continuous pour

Over 20,000m3 of nuclear-grade concrete was poured using concrete pumps

Over 20,000m3 of nuclear-grade concrete was poured using concrete pumps

Workers building the Hinkley Point C nuclear power station have completed the 49,000-tonne base for the station’s second reactor. The pour was completed on schedule – meeting a target date set more than four years ago. The final concrete pour of 8,991m3 set a new UK record for a single, continuous pour. It surpasses by 37m3 the previous record during construction of the base for Hinkley Point C’s first unit in June 2019.

The final concrete pour for Unit 2 continued around the clock

The final concrete pour for Unit 2 continued around the clock

This major milestone in nuclear construction was completed by teams that have had to adapt to new Coronavirus working conditions. Their achievement, known as “J-zero”, comes less than a year after the completion of the first reactor’s base in June 2019. It is the second major goal in 2020 and the successful completion of both follows the achievement of all the project goals in 2019. The date for achieving J-zero on Unit 2 was set more than four years, before the final investment decision was taken.

Final section of the 20,693m3 of concrete being poured into the foundation of Unit 2's Nuclear Island

Final section of the 20,693m3 of concrete being poured into the foundation of Unit 2’s Nuclear Island

Construction during the current Coronavirus crisis was able to continue after the project took a wide range of steps to ensure the safety of workers and the community. This included reducing numbers on site to enable social distancing and concentrating on the most critical areas of construction.

New Fareham Depot open for business

As part of our continued drive to provide the highest levels of service and reliability Camfaud have invested in a new multipurpose facility on the South Coast. Now open for business, our new Fareham depot has increased space for secure fleet parking and a new fully equipped service and repair facility. Following an extensive refit it also boasts ample storage for spares and ancillary equipment as well as new offices for the operations, sales and hire desk teams. This new regional operating centre supports our South Coast, South West and South Wales customer base and underlines our commitment to evolve and improve the business through investment in the necessary infrastructure. Orders 01329 232220.

New Fareham Depot

 

A14 Cambridge to Huntingdon improvement scheme

The A14 Cambridge to Huntingdon improvement scheme has opened more than 6 months early. Congratulations to Highways England, the Costain, Skanska, Balfour Beatty jv and especially to the Camfaud team that did such sterling work on this flagship project.

The A14 Cambridge to Huntingdon improvement scheme - now open

The A14 Cambridge to Huntingdon improvement scheme – now open

Pumping a bridge deck on the A14 Cambridge to Huntingdon improvement scheme

Pumping a bridge deck on the A14 Cambridge to Huntingdon improvement scheme

Returning to work

Social distancing - placing concrete from an M47 boom pump

Social distancing – placing concrete from an M47 boom pump

After the initial reduction in work due to the Covid-19 pandemic, the signs are that the construction industry is slowly but surely returning to work. To meet our customers’ needs, we are bringing more staff back from their furlough and look forward to a time when we are back to full strength again. Let’s hope it won’t be too long.