Pumping into the bottom of a shutter
Mowlem Building had to
construct seventeen reinforced concrete columns in the
basement of a partially built office block in
Newcastle-under-Lyme. The columns were to be formed from
the sheet piling faced with permanent steel shutters and
had to extend from the basement floor to the ring beam.
The original plan was to fill the columns through a
letter-box near the top of the shutter. However, this
solution was fraught with practical difficulties; how to
get the concrete to the top of the shutter, how to
prevent segregation, how to compact the concrete and how
to fill in immediately below the ring beam. Camfaud
suggested pumping from the bottom of the formwork through
pipes welded to the shutter. We provided seventeen stub
pipes which were then welded over the injection points. A
shut-off valve was then coupled to each stub pipe.
On the day of the pour, Camfaud supplied an M24 pump
complete with an operator experienced in this pumping
technique. The boom was threaded through the steel frame
buildings and down into the basement. Approximately 40
metres of pipeline were connected from the end of the
boom to the first shut off valve. The concrete was pumped
steadily into the first shutter with the level of
concrete being monitored. The pump was slowed as the
shutter filled and was stopped as soon as the concrete
grout seeped from the top of the shutter. Once the
shutter was filled, the gate valve was closed, the
delivery hose disconnected and the line coupled up the
next shutter.
This process was repeated a further seven times. At the
end of the day, the pipeline was stripped down and
cleaned out. The following day the pump returned, the
shut-off valves were removed, cleaned and coupled to the
next batch of shutters and the pumping process
re-commenced with the final nine shutters being filled.
At the end of the second day, the pipeline was stripped
down cleaned and stored back on the pump. The shut off
valves were stripped and cleaned following day. After two
days work, all seventeen columns had been concreted from
floor to ring beam above with no problem from concrete
segregation or voiding.
Pump: M24
Customer: Mowlem Building
Site: Newcastle under Lyme
Concrete Supplier: Tarmac Topmix
Date: December 2004
Customer: Mowlem Building
Site: Newcastle under Lyme
Concrete Supplier: Tarmac Topmix
Date: December 2004

