Round the clock pumping
During spring 2005 Camfaud
supplied pumps to Hochtief (UK) Construction on their
contract to build an "Electricity from Waste" Plant at
Allington, near Maidstone. Once operational, household
waste from Kent will be incinerated at the plant to
produce electricity which will be fed into the National
Grid.
The construction method chosen to build the two waste
bunkers and stair cores was slipforming. This method
requires the supply of concrete into a shutter on a
continuous basis with the shutter being raised as the
structure progresses. The bunkers were 41.8 m. high and
58.2 m. x 21.5 m. cross-section; the stair cores 35.5 m.
high with a 6.25 x 17.35 m. cross-section. The total
slipformed surface was 17,500 square metres.
While these structures were being constructed, Camfaud
provided 2 x M52 boom pumps working 24 hours / day, seven
days a week. The largest of the pours lasted for four
weeks and the smaller pours for two weeks each. Once the
plant is completed, planning permission requires that the
building is hidden by earth bunds constructed up to the
same level as the roof.
Pump: 2 x
M52
Customer: Hochtief (UK) Construction
Site: Allington Waste Incinerator
Concrete Supplier: Hanson
Date: Spring 2005
Customer: Hochtief (UK) Construction
Site: Allington Waste Incinerator
Concrete Supplier: Hanson
Date: Spring 2005

